Example Asbestos Removal Projects in Long Beach

These seven example jobs in Long Beach, Seal Beach and Los Alamitos run from a bungalow teardown to a storefront survey. Each one lists what was sampled, what was removed, how long the work took and an estimated cost.

Positive materials removed from a 1920s bungalow before its teardown

Example project

Home
1920s bungalow in Long Beach with a detached garage at the back of the lot
Original request
Take the house down and build a new two-story home on the lot
Testing
A whole-house survey by a Cal/OSHA-certified asbestos consultant, about 24 samples from floors, ceilings, walls and the old heating pipes
Found
Asbestos in the kitchen and bath floor tile and mastic, the ceiling texture in three rooms and the wrap on the heating pipes
Clear
The plaster walls and the window putty
Area
About 420 sq ft of floor, 500 sq ft of ceiling and 20 ft of pipe wrap
Timeline
Notice no later than 10 working days ahead, then seven working days before the wrecking crew
Cost
$24,000

Scope of work

Removal of every positive material in the survey, the district notice, rooms sealed in turn under air filters, wet removal into labeled bags, air monitoring and the haul with its paperwork. The survey, the demolition itself and the permit are separate.

Project overview

In this example, a family in Long Beach is replacing a 1920s bungalow with a new two-story house. Any demolition needs the district notice, so the whole-house survey comes first and the positive materials come out before the wrecking crew arrives.

Before the city issues the demolition permit, the district must have received the notice, and a copy goes to the Development Permit Center. The abatement company files the notice online, and the owner brings the copy to the counter.

The goal

The goal is a house with every positive material gone, so the wrecking crew can start on the day the permit allows.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples every room and the old heating pipes.
  2. Before work The contractor files the district notice online, and a copy goes to the Development Permit Center with the application.
  3. Days one to seven Room by room the floors, ceilings and pipe wrap come out wet, and the bags leave with a licensed hauler.
  4. Last An independent consultant checks the air, and the wrecking crew starts.

Planning right

  • Order the survey as soon as the teardown date is planned.
  • Keep the district notice and the lab report together for the permit counter.
  • Ask the wrecking crew to wait for the air results.
  • Give the neighbors the work dates.

Get a free quoteMore about renovation and demolition abatement

Wall plaster removed in a fourplex before new wiring goes in

Example project

Building
1940s fourplex in Long Beach with a vacant ground-floor unit
Original request
Rewire the vacant unit, opening the plaster walls of the hall and two rooms
Testing
A Cal/OSHA-certified asbestos consultant samples the plaster in each room and the kitchen wall compound
Found
Asbestos in the hall and bedroom plaster
Clear
The kitchen wall compound
Area
About 380 sq ft of wall
Timeline
Notice no later than 10 working days ahead, then four working days
Cost
$5,800

Scope of work

Containment around the vacant unit with its own air filter, wet removal of the positive plaster to the lath, bagging, a cleanup and the haul. The survey, the clearance air test, the wiring and the new walls are separate.

Project overview

In this example, the owner of a 1940s fourplex in Long Beach is rewiring the empty ground-floor unit before re-renting it. The electrician will open the plaster walls of the hall and two rooms to pull new cable.

A fourplex is not a single-unit dwelling, so the survey applies however small the job. The hall and bedroom plaster test positive and the crew removes it with the other three units occupied.

The goal

The goal is bare lath in the vacant unit, so the electrician can work without disturbing positive plaster.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the plaster in each room before the walls are opened.
  2. Before work The contractor files the district notice online and the owner tells the other tenants the work dates.
  3. Days one to four The unit is sealed from the common hall, and the positive plaster comes off wet to the lath.
  4. Last An independent consultant tests the air, and the electrician starts.

Planning right

  • Tell the other tenants the dates and where the crew will enter.
  • Keep the kitchen wall, which tested clear, for the electrician.
  • Plan the new walls only after the air results.
  • Keep the report with the building file.

Get a free quoteMore about drywall, joint compound and plaster removal

Textured ceiling removed from a condo before new recessed lights

Example project

Home
1960s condominium in Seal Beach with a living room and dining area under one textured ceiling
Original request
Replace the old ceiling fixture with recessed lights and a smooth finish
Testing
A Cal/OSHA-certified asbestos consultant samples the living room texture and the dining area texture
Found
Asbestos in the ceiling texture
Area
About 190 sq ft of ceiling
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$2,400

Scope of work

Two texture samples, the district notice, the unit sealed in plastic with air filters, the texture wetted and scraped into bags, a cleanup and the haul. The clearance air test, the new lights and the finish are separate.

Project overview

In this example, the owner of a Seal Beach condominium wants recessed lights and a smooth ceiling in the living and dining area. A condominium is not a single-unit dwelling, so the single-unit shortcut for small jobs does not apply.

Both samples test positive. The crew seals the unit, removes the texture in two working days and the electrician installs the lights after the air test.

The goal

The goal is a bare ceiling, so the new lights and the smooth finish go in on clean board.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant takes two samples from the ceiling.
  2. Before work The contractor files the district notice online, and the owner lets the building manager know the work days.
  3. Day one The doorway and vents are sealed and the texture is scraped wet.
  4. Day two A wipe-down, bagging and the haul, then an independent consultant takes air samples.

Planning right

  • Take everything off the walls and out of the room first.
  • Tell the building manager which days the crew needs the stairs and a parking space.
  • Install the lights only after the air results.
  • Share the report with the association.

Get a free quoteMore about popcorn ceiling removal

Wrapped attic ducts removed when a furnace is replaced

Example project

Home
1960s tract house in Los Alamitos with a furnace in the hall closet and ducts through the attic
Original request
Replace the furnace and the whole duct system
Testing
A Cal/OSHA-certified asbestos consultant samples the duct wrap at the furnace, the middle of the attic and the far bedroom run
Found
Asbestos in the wrap on the main trunk and the branch ducts
Clear
The tape at the register boots
Area
About 180 ft of duct in the attic
Timeline
Notice no later than 10 working days ahead, then two working days
Cost
$4,400

Scope of work

The attic hatch and the hall closet sealed, wet removal of the wrap and old duct into labeled bags, a cleanup and the haul. The survey, the clearance air test and the new ducts and furnace are separate.

Project overview

In this example, a family in Los Alamitos is replacing the furnace and ducts in their 1960s tract house. The rule counts installing or removing heating and cooling systems as renovation, so the survey comes before the old system is touched.

The wrap on the trunk and branch ducts tests positive. The crew takes it out first, then the heating company brings in the new system over clean framing.

The goal

The goal is an attic with the old wrapped ducts gone, so the new system goes in clean.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap at three places in the attic and at the furnace.
  2. Before work The contractor files the district notice online and the heating company holds its install date.
  3. Days one and two The hall closet and the attic hatch are sealed, and the ducts are wetted, cut and bagged.
  4. Last An independent consultant tests the air, and the heating crew starts the new system.

Planning right

  • Clear the hall closet shelves ahead of time.
  • Ask the heating company to start after the air test.
  • Keep the lab report with the permit papers.
  • Plan for the house to be without heat for a day or two between systems.

Get a free quoteMore about HVAC duct and pipe insulation removal

A storefront suite surveyed room by room before a tenant improvement

Example project

Building
1950s one-story storefront building in Long Beach, with a 1,400 sq ft suite for lease
Original request
A new tenant wants a larger front room, a new floor and a rebuilt back office
Testing
A Cal/OSHA-certified asbestos consultant takes about 24 samples across the floors, ceilings and walls of the suite
Found
Asbestos in the floor tile and mastic of the back room and in the back office ceiling texture
Clear
The front floor, the wall compound and the storefront trim
Timeline
One visit, then lab results and the report
Estimated survey cost
$3,200

Scope of work

A full-suite survey by the consultant, about 24 samples, lab results for each, and a report with a plan of the suite showing every sample spot. Removing the positive materials is priced on its own.

Project overview

In this example, a new tenant is taking a 1950s storefront suite in Long Beach and plans a larger front room and a rebuilt back office. The owner orders the survey before the lease work begins.

The back room floor and the back office ceiling test positive, the rest is clear. The report becomes the scope for the abatement bid, and the contractor works only where the plan shows a positive result.

The goal

The goal is a report that tells the owner and the tenant which rooms need removal before the work starts.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant walks the suite with the plans and takes samples in each room.
  2. Then Lab results arrive for every sample.
  3. Next The report goes to the tenant and to the abatement bidders.
  4. Then The positive materials are removed before the construction crew starts.

Planning right

  • Hand the consultant the tenant improvement plans before the visit.
  • Ask for a plan of the suite with each sample spot marked.
  • Keep the report with the lease file.
  • Schedule removal before demolition of the back office.

Get a free quoteMore about apartments and condos

Pipe wrap in a 1940s cottage tested before the water heater is replaced

Example project

Home
1940s cottage in Long Beach with a water heater in a closet off the kitchen
Original request
Replace the water heater and move its pipes a few inches
Testing
A Cal/OSHA-certified asbestos consultant samples the pipe wrap at two fittings, the closet floor vinyl and the wall texture
Found
Asbestos in the wrap at both fittings
Clear
The closet floor vinyl and the wall texture
Timeline
One visit, then lab results and the report
Estimated testing cost
$450

Scope of work

A visit by the consultant, four samples, a lab result for each and a short report with the sample spots marked. Taking the wrap off the pipes is priced on its own.

Project overview

In this example, a couple in a 1940s cottage in Long Beach is replacing an old water heater and needs a plumber to shift two pipe connections. Some of the old wrap on those pipes is cracked.

Four samples cover the wrap at both fittings, the floor and the wall. The wrap tests positive and the floor and wall are clear, so the plumber waits for the crew to take the wrap off before cutting the pipes.

The goal

The goal is a water heater swap that does not cut through positive wrap.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the wrap at both fittings, the floor and the wall.
  2. Then Results come back with two positive samples and two clear ones.
  3. Next The crew is booked to remove the wrap.
  4. Then The plumber starts on the new water heater.

Planning right

  • Keep the plumber out of the closet until the wrap is gone.
  • Do not take samples yourself, the consultant knows what to cut and how.
  • Keep the report with the house papers.
  • Ask for a plan with the sample spots marked.

Get a free quoteMore about asbestos testing and surveys

Corridor tile and mastic lifted in an eight-unit apartment building

Example project

Building
1960s two-story building in Long Beach with eight apartments off two corridors
Original request
Replace the worn corridor floors on both levels
Testing
A Cal/OSHA-certified asbestos consultant samples the corridor tile and mastic on both floors and at the stairs
Found
Asbestos in the 9-inch tile and the mastic under it
Clear
The stair treads
Area
About 1,000 sq ft of corridor floor
Timeline
Notice no later than 10 working days ahead, then four working days
Cost
$9,200

Scope of work

One corridor sealed at a time, tile lifted, mastic taken up wet, bagging, a cleanup and the haul with its paperwork. The survey, the clearance air test and the new floor are separate.

Project overview

In this example, the owner of an eight-unit building in Long Beach is replacing the corridor floors on both levels. Residents use the corridors every day, so the work is planned one corridor at a time.

The tile and mastic test positive. An apartment building is not a single-unit dwelling, so the survey and the district notice both apply, and the crew finishes the lower corridor before starting the upper one.

The goal

The goal is bare corridor floors one level at a time, so residents always have a clear path to their doors.

Process

  1. First visit A Cal/OSHA-certified asbestos consultant samples the tile and the mastic on both levels.
  2. Before work The contractor files the district notice online and the owner sends residents a schedule.
  3. Days one to four One corridor at a time is sealed, the tile is lifted and the mastic is taken up wet.
  4. Last An independent consultant tests the air before the new floor is laid.

Planning right

  • Give residents the corridor dates in writing.
  • Keep one stairway open throughout.
  • Order the new floor only after the air results.
  • Keep the report with the building file.

Get a free quoteMore about floor tile and mastic removal