Positive materials removed from a 1920s bungalow before its teardown
Example project
- Home
- 1920s bungalow in Long Beach with a detached garage at the back of the lot
- Original request
- Take the house down and build a new two-story home on the lot
- Testing
- A whole-house survey by a Cal/OSHA-certified asbestos consultant, about 24 samples from floors, ceilings, walls and the old heating pipes
- Found
- Asbestos in the kitchen and bath floor tile and mastic, the ceiling texture in three rooms and the wrap on the heating pipes
- Clear
- The plaster walls and the window putty
- Area
- About 420 sq ft of floor, 500 sq ft of ceiling and 20 ft of pipe wrap
- Timeline
- Notice no later than 10 working days ahead, then seven working days before the wrecking crew
- Cost
- $24,000
Scope of work
Removal of every positive material in the survey, the district notice, rooms sealed in turn under air filters, wet removal into labeled bags, air monitoring and the haul with its paperwork. The survey, the demolition itself and the permit are separate.
Project overview
In this example, a family in Long Beach is replacing a 1920s bungalow with a new two-story house. Any demolition needs the district notice, so the whole-house survey comes first and the positive materials come out before the wrecking crew arrives.
Before the city issues the demolition permit, the district must have received the notice, and a copy goes to the Development Permit Center. The abatement company files the notice online, and the owner brings the copy to the counter.
The goal
The goal is a house with every positive material gone, so the wrecking crew can start on the day the permit allows.
Process
- First visit A Cal/OSHA-certified asbestos consultant samples every room and the old heating pipes.
- Before work The contractor files the district notice online, and a copy goes to the Development Permit Center with the application.
- Days one to seven Room by room the floors, ceilings and pipe wrap come out wet, and the bags leave with a licensed hauler.
- Last An independent consultant checks the air, and the wrecking crew starts.
Planning right
- Order the survey as soon as the teardown date is planned.
- Keep the district notice and the lab report together for the permit counter.
- Ask the wrecking crew to wait for the air results.
- Give the neighbors the work dates.